December 18, 2015

 

The following work was accomplished over past few weeks:
  • Roofing system for area "A" is nearly complete and area "B" has been started.
  • Underground mechanicals for area area "D" (Auditorium, Instumental Music, World Language) completed.  Slab on grade concrete was poured earlier this week.
  • Exterior wall framing and sheathing completed.
  • Exterior masonry brick work mostly completed in areas "A", "B"  and the interior courtyard.
  • Layouts and framing for interior spaces completed in area "A" and started in areas "B" and "C".
  • Topsoil screened and relocated on the site.  See further information below.
  • Preparation of window and curtain wall frames for installation has begun.  Cafeteria, gym and west side entrance completed,
  • Binder course of paving for the pre-K drop-off and parking area on the east side of the site completed.
  • Installation of internal electrical and plumbing systems has begun in areas "A" and "B".
  • Installation of sheet rock has begun in area "A".

Work anticipated over the next few weeks:
 
  • Layouts and framing for interior spaces will continue in areas "B" and "C".
  • Topsoil that was removed from the site in the spring and stored at DPW will be screened and returned to the site.  See separate note below.
  • Installation of the roofing system will continue in area "B" and start in area "C"
  • Continue to prepare window and curtain wall frames and begin the installation.
  • Exterior masonry brick work will continue in area "C" and "D".
  • Installation of internal electrical and plumbing systems will continue in areas "A" and "B".
  • Installation of sheet rock will continue in areas "A" and "B"

 

IMPORTANT:  Starting on Saturday, December 19, 2015, topsoil being relocated back to the project site from DPW will be stockpiled in the area between the track at Sterling Field and the existing school building.  Access to Sterling Field will be through the school parking lot off of Flatbush Avenue.  The stockpiled topsoil will be fenced, seeded and treated with lime to contain any potential odor issues.  Hauling of the topsoil will not occur on school days but on Saturdays and during the Holiday Recess.  Attached is the plan associated with this activity.

Below are a few pictures of the construction.

As always, if you have a concern, please get in touch with myself, the project manager or the project superintendent listed below.
 
 
Thanks, 
Bob Palmer
Director of Plant and Facilities Services
860 748-0743 - cell
 
Jeff Luzzi
Project Manager - Fusco Corp.
 
Joe LaPera
Project Superintendent - Fusco Corp.
203 627-4707 - cell
Pictures: 
Auditorium sloped seating concrete slab poured, stage and adjacent areas ready to be poured


Windows being installed at west entrance

Upcoming Events

Charter Oak International Academy

425 Oakwood Ave., West Hartford, CT 06110

Juan Melián, Principal

T: 860-233-8506

F: 860-231-9654

email page print page small type large type
powered by finalsite