The following work was accomplished over past few weeks:
  • Drilling for the geothermal wells continued.  We have completed 61, 3 to go!!
  • Underground storm water system on the east side system continued and is complete.
  • Steel erection and detailing work continued.
  • Underground mechanicals for area "A" (Offices, Cafeteria, Gym areas) completed and area "B" (classrooms and media center) started.
  • Roof drains were installed.
  • Masonry fire walls were installed.
  • Exterior wall framing and sheathing began in area "A".

Work anticipated the week September 21-25:
 
  • Drilling for the geothermal wells will continue and should be completed by end of the week.
  • Steel detailing work will continue.
  • Installation of concrete for slab on grade for area "A" will occur on Monday, September 21st.  There were will be approximately 20 concrete trucks making deliveries to the site.
  • Installation of underground mechanicals in preparation for slab concrete installation in area "B" will continue.
  • Exterior wall framing and sheathing will continue.
  • Install base material in preparation of paving for the pre-K drop-off and parking area on the east side of the site.

Upcoming Events

  • January 2018
    • MonJan22 Student-Led Star Assembly PreK-1 2:00 PM to 2:30 PM
    • MonJan22 Student-Led Star Assembly 2-5 2:45 PM to 3:15 PM

Charter Oak International Academy

425 Oakwood Ave., West Hartford, CT 06110

Juan Melián, Principal

T: 860-233-8506

F: 860-761-1244


email page print page small type large type
powered by finalsite