The following work was accomplished last week:

  • Drainage work at the intersection of Sidney and Oakwood Avenues was completed.

  • Several foundation excavations and concrete pours were made.

  • Gravel for stabilization and foundation back filling continued to be brought to the site.

  • The electrical re-feed of the existing building from Flatbush Avenue was completed on Saturday.

  • Drilling for the geothermal wells commenced.

  • Installation bean of the underground storm water system at the north end of the site.

 Work anticipated this week:

  • Demolition of the utility service poles along the former Parker Street will commence.

  • Enabling work for the re-routing of the sanitary line to the existing building will continue along the west side of the site.

  • Geothermal well drilling contractor will continue.

  • Foundation excavations and concrete pours will continue.

Upcoming Events

  • May 2017
    • MonMay29 No School- Memorial Day
  • June 2017
    • FriJun02 Spring Picnic 5:30 PM to 8:00 PM

Charter Oak International Academy

425 Oakwood Ave., West Hartford, CT 06110

Juan Melián, Principal

T: 860-233-8506

F: 860-231-9654

email page print page small type large type
powered by finalsite